300 tonnes of duplex piping for an offshore platform expansion

Tier-1 EPC contractor

300 MT
Material delivered
6 weeks
Lead time
NACE MR0175
Documentation

When an EPC contractor's primary supplier missed a critical milestone for an offshore platform expansion, Icon Steel was brought in to recover the schedule. Working with the client's engineering team, we matched 80% of the requirement from our Dubai stock and expedited the balance directly from our group mill.

Full NACE MR0175 documentation, complete with welding consumables qualification packs, was delivered with the shipment.